Earned Value Managment - EVM. Why is it so important?
Earned Value Management (EVM) has always been challenging to understand. EVM covers 4 to 5 questions in the exam. I am going to narrate an example to explain this concept:
Q – A company ABC is hired to install underground pipes for water supply to metropolitan city. Total length is 9 km. The cost is $ 30/Ft. Project duration is 6 months. Today 2nd month is completed. The Company has installed pipes over 1.8 km. The Cost incurred is $ 185,000.
Calculate CV, CPI, SV, and SPI?
A – First need to calculate EV. EV is Budgeted cost multiplied by % complete i.e.
EV = Budgeted Cost x % Complete
The Cost to install one running foot of pipe is $ 30. The Total distance is 9 km. The Cost is expressed per running feet and distance is taken in Kilometer. So unit conversion is required. Convert cost and distance into the same unit. Therefore Budgeted Cost is
Budgeted Cost = Total Cost (Some of PV)
= $ 30/ft *9 km
= $ 98.425/m * 9000 m
= $ 885,825
Budgeted Cost (BC) = $ 885,825
1.8 km is complete so far. It means
% complete = 1.8/9
= 0.2
= 20 %
% complete = 20 %
EV = 885,825 x .20
Ev = 177,165
Now Calculate
1 – Cost variance (CV):
CV = EV-AC
= 177,165 – 185,000
= – 7,835
CV = – 7,835
2 – Cost Performance Index (CPI):
CPI = EV/AC
= 0.95
CPI = 0.95
3 – Schedule Variance:
SV = EV – PV (Planned Value)
= 177,165 – 295,275
= – 118, 120
SV = 118,120
4 – Schedule Performance Index (SPI):
SPI = EV/PV
= 177,165/295,275 = 0.6
Project is cost overrun and behind schedule
* One ft is 304.8 mm, one m to1000 mm.
**PV is calculated as: